[Developers] If clauses in schedule
Frank Loeffler
frank.loeffler at aei.mpg.de
Tue Apr 8 10:34:55 CDT 2008
On Tue, Apr 08, 2008 at 10:20:56AM -0500, Erik Schnetter wrote:
> The new if clauses do not affect the order in which scheduled items are
> executed. The schedule is constant in time, but certain elements are
> skipped depending on certain conditions. A schedule description
Thanks, I now understand that the new 'if' cannot possibly do all the
things the old one can and vice versa. So, I now support your proposal.
Also the syntax now makes more sense for me.
Frank